CATEGORY prefab
Modern Prefab house in Lincoln: Almost Done!

We are a few days away from move-in day at our Lincoln project, so we closed the studio for a few hours and everyone took a pre-Certificate-of-Occupancy look. Yes, there is a bit of a final punch list (as always), and Lincoln’s new Building Inspector brought up a few last minute concerns (also not unexpected), but on this gorgeous spring day, the sun shone gloriously, and we could all imagine the joy we hope our clients will feel once they are fully ensconced in their new home…
Will Ruhl
- Street façade with living / dining volume on the right, guest bedroom on the far left, and roof deck in the middle.
- Screened porch with NanaWall bi-folding doors connecting to the living / dining area, and listening room and home office volume above.
- Street façade with stone steps leading up to 3-story entry / stair hall.
- Roof deck between main living spaces and bedrooms, and adjacent to kitchen.
- LR fireplace with honed Botticino surround and spark fire fireplace is detailed to float above the quartersawn red oak floors.
- Stair screen wall holds up the custom steel stair, and has cutouts to allow light and selective views between the double height living space and stair.
- Custom steel stair with 2×6 steel channel stringers, flat bar posts, stainless steel cable rails, and quartersawn red oak treads and handrails.
- Custom steel stair close-up view at landing.
Construction Update: Lincoln Custom Prefab House

The custom prefab house we designed in Lincoln is nearing completion, and the owners are getting excited about moving out of their temporary apartment and into their new, sun-filled dream house! The cedar tongue and groove siding looks fantastic; it has a temporary protective coating and will be stained in the spring after studying some color options. There is a lot of frantic activity inside also, with the quarter sawn red oak flooring being finished this week, tile and trim almost complete, the stainless steel cable railings being installed, and the Pedini kitchen getting final adjustments.
- The new house as seen from the street. The main living spaces are within the cube on the right, and bedrooms are on the left.
- Looking up from the garage to the new front door and three-story stair hall beyond. In the middle is a sun-filled roof deck.
- View of the west end of the house, with master bedroom in the left volume and guest bedroom in the right volume, separated by a narrow corridor.
- The north and east sides of the house include a large screened porch, with home office and listening room above.
- The new open riser steel stair, awaiting its stainless steel cable guard rail and quarter sawn red oak treads.
- Between the double height living room and stair is a floating planar wall with openings cut in to allow views and light to pass through.
Progress at our custom prefab Lincoln House
We are thrilled to be able to update you all on the progress being made at our modern custom prefab house in Lincoln, MA. All of the double height windows are installed at the two-storey-high living room and stair hall, eight 6×6 steel columns have been carefully inserted around the double height spaces, the Nanawall doors are installed between the dining room and screened porch, the roof and skylights are complete and water tight, and there has been a ton of plumbing, electrical, HVAC (geothermal), and listening room work performed inside. Exterior siding will start being installed this week, so everyone is hoping for continued un-seasonably-warm weather, and looking forward to the green zip-system sheathing to be covered in cedar! FOMA (Friends of Modern Architecture in Lincoln) should be pleased that the house is suitably modern, as they required during permitting; how wonderful (and unusual!) for a town to take a stand against cookie-cutter-McMansions! Check out the photos below, and let us know what you think!
- The front of the house, seen from the street. On the right are the double height living room and stair hall, and on the left is the guest room, with the exterior roof deck between.
- A closer look at the double height windows at the living room and stair hall. The new windows will bring much-needed sunlight deep into the main living spaces, and will also allow expansive views to the outside from the top floor home office.
- On the side of the house, a tall window defines the two-storey living room, a large picture window defines the dining room, and a long low window defines the upstairs home office; each window is customized for its space and function.
- Barely visible in the shadow of the screened porch is a twenty-one foot wide Nanawall door system that will allow continuous passage between the porch and dining room, blurring the line between inside and outside. The screened porch will also have a sculptural fireplace for three-season use.
- On the north side of the house, the study / listening room volume cantilevers beyond the screened porch, with the master suite extending out to the west. The collage of volumes breaks down the overall mass of the house, helps visually “lock” the house into its landscape, and marks the original factory-built modules.
- Off of the master suite will be a sculpted rock garden, designed by the landscape architect, Matthew Cunningham; you can see an earlier rendering of this garden, as well as Matthew’s plan, on our April 11, 2011 blog post.
- At the west end of the house, a window in the master bedroom looks deep into the property, with lovely views of the woods.
- Tis the season!
Modern Prefab House “set” in Lincoln

After months of planning, the eight modules for the modern prefab house Ruhl Walker custom designed for a site in Lincoln, MA, were delivered from Pennsylvania and “set” (the term custom modular prefabrication companies use for the assembly of the modules) last week. The original set plan anticipated by Haven Custom Homes was for a single long day, but thanks to some unexpectedly difficult site constrictions and then a day of steady rain and thunderstorms, the set ended up taking three full days. Managing the process was the team from Sea Dar Construction, as well as a set crew from Haven, with Ruhl Walker Architects on site to help solve any architectural challenges that might arise (and we must admit that watching a “set” can be a whole lot of FUN; in fact, the whole studio turned out to watch).
In hindsight, it was brilliant that our clients decided NOT to build through last winter and its record setting snowfalls, but now it’s almost October, and it would be an understatement to say that everyone was more than ready for some serious action! Fortunately, that is one thing that you can rely on from prefab / modular: one day all you have is a foundation and piles of dirt, and the next day you have an almost entirely finished house, complete with plastered walls, interior trim, windows and doors, lighting fixtures and wiring, plumbing systems, sprinkler system, and in this case even a highly customized Listening Room / Home Theater. There is still a lot of work to do to finish both the inside and outside of the house, but all of a sudden there is A LOT to get excited about.
DAY ONE:
Haven Homes has spent the last month fabricating the modules, including ordering and obtaining all of the custom selected materials, packaging / weather-proofing the factory built modules and making everything safe for the eight hour drive through four states, as well as strategizing the set. Every state has slightly different regulations regarding transporting prefabricated modules, including maximum widths, heights, and lengths and whether it is necessary to schedule State Police escorts. The modules left the factory on a Monday and were delivered to a temporary staging site in Lincoln on Tuesday, ready for the set to start at seven the next morning.
A team from Haven had previewed the route and mapped out a strategy, and the first day began with a dry run with one of the smaller modules. All seemed fine, so they want back to the staging area (it is necessary to reserve / rent a staging area prior to the set unless you happen to have a huge, open, easily accessible area next to your foundation!) and loaded up one of the largest modules. The plan was to start at the back of the house, work their way forward, then finish with the three modules on the second floor. However, Murphy’s Law holds for every type of construction, including prefab, and the first module to be delivered took many hours longer than anticipated to get around the last two corners. Trees were closer to the road than anticipated, a power pole was tilting at just the wrong angle, power lines were just a hair too low, and the rig pulling the modules had a turning radius that just didn’t meld with the side street’s geometry. Fortunately, modules two and three were shorter and went in much faster, but the day ended prematurely with the State Police closing the set down, forcing Haven to park module four overnight on a very patient and forgiving neighbor’s front yard so as not to disturb rush hour traffic…
DAY TWO:
After overnight thunderstorms and heavy downpours, there was some question as to whether day two would be a total washout, but the rain had become a light drizzle by 9:00 so the teams reassembled and prepared module number four for its short trip from the neighbor’s front yard to our clients’ foundation. More good news was the discovery that the previous night’s efforts to make the installed modules water tight was a success.
Module number four is the longest of the eight modules, and includes the front lower section of the living room at one end, an open roof deck in the middle, and a guest bedroom on the other end. This inherent asymmetry made the prep work for being craned into place much more delicate than for the other modules. Instead of the usual two cables being fed through the perimeter floor structure, this module required four, and this work had to be redone several times to insure that the module was balanced perfectly. With a new band of thunderstorms on the way, the set was closed down after module number four was set in place, and the house was buttoned up for another rainy night.
DAY THREE:
We awoke to an absolutely beautiful, sunny day today, and therefore the third day of set began on a high note. The final three modules are all substantially smaller than the others, and were to be installed above the modules from the previous two days. The first module of the day was the Listening Room, which ended up resting gently within the edge of the canopy of an existing maple tree, which should provide spectacular views this fall! The second and third (final) modules house the upstairs home office as well as the upper half of the living room and main stair. All three modules were installed by lunch time, and then the process of making the entire structure weather and water tight commenced.
The next steps are to install the roof parapets and final rubber membrane roofing, remove any temporary framing (for instance the temporary shoring at the double height living room and stair hall, as well as at the twenty-one foot long by eight foot high Nanawall opening), install the skylights and double height windows in the living room and stair hall, install all the exterior siding and trim, and finish off the interiors (tile, cabinetry, wood flooring, custom steel stair, etc.).
See our post from April 8th to see a digital preview of what the house will look like. Lots to do before Thanksgiving… Keep checking back to see updates!

In 2007, Ruhl Walker Architects was hired to design six faculty houses for St. Mark’s School in Southborough, MA, prevailing over three architectural firms with much deeper portfolios of previous institutional work. We may have been the most surprised of anyone, but our decades of experience designing environmentally responsible single family houses, our initial concept that attempted to design not just a few small houses but also a coherent landscape and campus strategy, and our unusual design team – which included the prefabricator, Empyrean, as well as our “green” mechanical engineer, Sergio Siani of Norian / Siani, whose practice was all about sustainable design before such a thing existed in the press – managed to win the day . How else was someone going to meet St. Mark’s “impossible” schedule – less than a year for design and construction – and “impossible” budget, without a prefabricator on board from day one? And sustainability is a key element of the Head of School’s mandate to transform the 150+ year old campus. We embarked on this “impossible” project with open minds, and thanks to our fabulous team as well as an excellent general contractor – Cutler Associates of Worcester, MA – a super Owner’s Rep – Lee Sollenberger of Design Technique of Newburyport, MA – and a decisive Building Committee, were able to finish the project (see on our portfolio website) under budget and several months early.
As the faculty houses were being completed, St. Mark’s was also embarking on an ambitious master planning process. The planning goals included further campus consolidation and sustainability initiatives, in particular upgrading their main campus building, a meandering structure dating back to 1866 that includes classroom and administrative space, a chapel, dining and cooking facilities, dorm rooms, and faculty apartments. In order to be able to begin renovating and upgrading the existing living spaces without reducing the size of the student body or number of faculty, additional faculty and student housing had to be built elsewhere on campus. A previously undeveloped site within an existing row of faculty houses was identified, and the decision was made to reassemble our team to design a new two-family faculty house. Due to the small size of the project, the decision was made to do the mechanical design as a design/build effort, but Rebecca Bachand of UBLA joined us again for the landscape design.
The schedule we were presented was substantially tighter than the first project, along with an even more challenging budget. So this time around, we decided to pursue custom modular construction rather than panelized construction, so that we could have the living spaces fabricated over the winter in a factory while site work was being completed, and this decision proved to be fortunate as we accumulated historic quantities of snow. Last week the eight modules were delivered to the site by Simplex Homes just as the local general contractor was putting the finishing touches on the foundation. The modules came complete with all windows, interior wall finish and trim, rough and finish electrical and plumbing, kitchen and bath cabinetry, essentially everything except exterior siding and interior flooring. And we are on schedule to have the units ready for move-in by June.
Here are some images from the module “set”:
In Design: Custom Prefabricated House in Lincoln
This house started as a substantial renovation of an existing 50′s vintage modern house in Lincoln, MA. Because the original program included a large laundry list of renovations to the existing house systems, once we began working with general contractors on a budget for the renovation project it became clear that the cost of renovating was going to be comparable to the cost of building a new house. In the interest of making as energy efficient a house as possible, maximizing long term value for the owners, and minimizing short term disruption to the owners, the decision was made to pursue a new house on the existing foundation, with the new house being built by a modular prefabricator for substantial time and cost savings. Both of the owners write software and manage companies from home, so minimizing disruption is critically important; pursuing modular construction will help minimize the time the owners will have to be out of their house during construction. The basement level will be reconfigured to accommodate a new, expanded garage, an exercise room, mudroom, wood working shop, bathroom, and mechancial and storage rooms. The main level will have a large, open living / dining room, screened porch with fireplace, enlarged kitchen with pantry, master suite, guest bedroom, and south-facing courtyard / roof deck. On an upper level will be an A/V room, a large home office, and a bathroom. During the Permitting process, a group called Friends of Modern Architecture in Lincoln was consulted by the Town, to make sure that the modern house that was being partially demolished would be replaced with a suitably contemporary replacement, and we of course passed the test. The house will be prefabricated by Haven Homes and site fabricated by Sea Dar Construction of Boston. Landscape design will be by Matthew Cunningham. The house is currently in design, with shop drawings being prepared by Haven Homes, and custom interior and exterior detailing by Ruhl Walker Architects. Construction is expected to be completed by October.






















































